Gas Treatment Plant at Hakl Zohr – Port Said

The project is the construction of field which is one of the most important projects for the development of natural gas fields being implemented. The companies operating in the field of oil and gas classified the field as the largest gas discovery in the Mediterranean Sea and one of the largest discoveries on the global level.

EGYDRILL company has contracted to execute nearly 35% from the piling scope in project.                                                   
Egydrill scope of works are divided two stage as the following:

Type
Length
No Of Piles
Total Lengths
Remark
Bored Piles 602016
120960
80 cm Dia (First Stage)
Bored Piles
601200
72000
80 cm Dia (Second Stage)
Bored Piles
60231
13860
100 cm Dia (Frist Stage)
Trimming Works
3391
3391

Technical Challenges: the Company have eleven piling machine in the project, in addition to eight cranes and all accessoires which are necessary to complete the ٍ scope of work on time
 
 

Project name: Zohr development project.

Location: Port Said.

Client: PETROBEL & ENI.

Main Contractors: PETROJET

 

Starting date:

  • Frist Stage: 16/6/2016 
  • Second Stage :1/4/2017.

Completion date (estimated):

  • 5/15/2017